Land Development System (easyACCESS) Replacement - Foundation (YV Water) appears in 2 snapshots of the Victorian IT dashboard, from 2023-24 Q1 to 2023-24 Q2.
Its cost is $6.8m at 2023-24 Q2, against $2.7m at its baseline: +153%.
Its planned finish is 31 Oct 2023, 32 months earlier than the 30 Jun 2026 first planned.
Its latest rating is Green (2023-24 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Land Development System (easyACCESS) Replacement - Foundation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwaterlanddevelopmentsystemeasyaccessreplacementfoundation, as at 18 May 2026. Licence: CC BY 4.0.
How much does Land Development System (easyACCESS) Replacement - Foundation cost? Its cost is $6.8m at 2023-24 Q2, against $2.7m at its baseline: +153%.
Is Land Development System (easyACCESS) Replacement - Foundation late? Its planned finish is 31 Oct 2023, 32 months earlier than the 30 Jun 2026 first planned.
What is Land Development System (easyACCESS) Replacement - Foundation's latest rating? Its latest rating is Green (2023-24 Q2).