Victorian IT Project Dashboard: 67% of 966 projects now cost more than their baseline figure, as at 18 May 2026.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard. Tollgate Data, https://data.tollgatehq.com/datasets/vic-itd, as at 18 May 2026. Licence: CC BY 4.0.
What share of Victorian IT dashboard projects cost more than their baseline? 67% of 966 projects now cost more than their baseline figure. Victorian IT Project Dashboard: baseline and current cost taken from the same row, the project's latest snapshot; nominal, no CPI adjustment.
How often does Victorian IT dashboard restate a project's plan? 68% of 906 projects cost more than the original plan, 68% more than the current one. Victorian IT Project Dashboard: the 906 projects seen in at least two snapshots that carry a planned cost.
What share of Victorian IT dashboard projects finish later than planned? The source reports 87% of 1161 projects finishing late. Victorian IT Project Dashboard: calendar months between the baseline and the current completion date, both on the latest row.
What share of Victorian IT dashboard projects were delivered on plan? 11% of 555 completed projects came in at or under plan on both cost and date. Victorian IT Project Dashboard: the projects the source marks completed that carry a baseline and a current figure for both cost and completion date.
How many Victorian IT dashboard projects are rated Red? 9.8% of the 244 projects rated in 2025-26 Q2 were Red. Victorian IT Project Dashboard: status as the source published it at each snapshot.
How long before a Victorian IT dashboard project is first downgraded? The 177 projects that were downgraded took a median 9 months to reach Amber/Red or worse. Victorian IT Project Dashboard: months between a project's first rated snapshot and the first one rating it Amber/Red or worse, over the projects rated in at least two snapshots.
Do bigger Victorian IT dashboard projects overrun more often? Cost sits above baseline for 62% to 71% of projects across the four size bands. Victorian IT Project Dashboard: share of projects above baseline cost, by quartile of project size. Association, not cause.
How many Victorian IT dashboard projects enter and leave each snapshot? 87% of the 2070 projects seen before 2025-26 Q2 are absent from it. Victorian IT Project Dashboard: each bar holds the projects continuing from the previous snapshot and those entering at this one, so it is that snapshot's own population.
What share of Victorian IT dashboard projects leave without a recorded outcome? 34% of the 1808 projects that left the register carried no completion or termination marker. Victorian IT Project Dashboard: a leaver is a project seen in an earlier snapshot and absent from the latest one, read off its last row.