Land Development in Salesforce (YV Water) appears in 8 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2022-23 Q4.
Its cost is $6.2m at 2022-23 Q4, against $2.7m at its baseline: +130%.
Its planned finish is 30 Jun 2030, 48 months later than the 30 Jun 2026 first planned.
Its latest rating is Green (2022-23 Q4).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Land Development in Salesforce. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwaterlanddevelopmentinsalesforce, as at 18 May 2026. Licence: CC BY 4.0.
How much does Land Development in Salesforce cost? Its cost is $6.2m at 2022-23 Q4, against $2.7m at its baseline: +130%.
Is Land Development in Salesforce late? Its planned finish is 30 Jun 2030, 48 months later than the 30 Jun 2026 first planned.
What is Land Development in Salesforce's latest rating? Its latest rating is Green (2022-23 Q4).