Enterprise Historian (YV Water) appears in 11 snapshots of the Victorian IT dashboard, from 2018-19 Q4 to 2021-22 Q2.
Its cost is $5.8m at 2021-22 Q2, against $4.8m at its baseline: +21%.
Its planned finish is 30 Jun 2022, 6 months later than the 30 Dec 2021 first planned.
Its latest rating is Amber (2021-22 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Enterprise Historian. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwaterenterprisehistorian, as at 18 May 2026. Licence: CC BY 4.0.
How much does Enterprise Historian cost? Its cost is $5.8m at 2021-22 Q2, against $4.8m at its baseline: +21%.
Is Enterprise Historian late? Its planned finish is 30 Jun 2022, 6 months later than the 30 Dec 2021 first planned.
What is Enterprise Historian's latest rating? Its latest rating is Amber (2021-22 Q2).