Distribution Management System (DMS) (YV Water) appears in 10 snapshots of the Victorian IT dashboard, from 2020-21 Q4 to 2023-24 Q1.
Its cost is $6.5m at 2023-24 Q1, against $6.0m at its baseline: +8%.
Its planned finish is 31 Dec 2023, 6 months later than the 30 Jun 2023 first planned.
Its latest rating is Green (2023-24 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Distribution Management System (DMS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwaterdistributionmanagementsystemdms, as at 18 May 2026. Licence: CC BY 4.0.
How much does Distribution Management System (DMS) cost? Its cost is $6.5m at 2023-24 Q1, against $6.0m at its baseline: +8%.
Is Distribution Management System (DMS) late? Its planned finish is 31 Dec 2023, 6 months later than the 30 Jun 2023 first planned.
What is Distribution Management System (DMS)'s latest rating? Its latest rating is Green (2023-24 Q1).