Core Switch Replacement (YV Water) appears in 9 snapshots of the Victorian IT dashboard, from 2019-20 Q3 to 2021-22 Q3.
Its planned finish is 31 Mar 2022, 13 months later than the 28 Feb 2021 first planned.
Its latest rating is Green (2021-22 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Core Switch Replacement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwatercoreswitchreplacement, as at 18 May 2026. Licence: CC BY 4.0.
Is Core Switch Replacement late? Its planned finish is 31 Mar 2022, 13 months later than the 28 Feb 2021 first planned.
What is Core Switch Replacement's latest rating? Its latest rating is Green (2021-22 Q3).