Application Program Interface (API) Integration (YV Water) appears in 7 snapshots of the Victorian IT dashboard, from 2018-19 Q4 to 2020-21 Q2.
Its cost is $1.3m at 2020-21 Q2, against $0.8m at its baseline: +62%.
Its planned finish is 30 Sep 2020, 7 months later than the 29 Feb 2020 first planned.
Its latest rating is Green (2020-21 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Application Program Interface (API) Integration. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/yvwaterapplicationprograminterfaceapiintegration, as at 18 May 2026. Licence: CC BY 4.0.
How much does Application Program Interface (API) Integration cost? Its cost is $1.3m at 2020-21 Q2, against $0.8m at its baseline: +62%.
Is Application Program Interface (API) Integration late? Its planned finish is 30 Sep 2020, 7 months later than the 29 Feb 2020 first planned.
What is Application Program Interface (API) Integration's latest rating? Its latest rating is Green (2020-21 Q2).