Project Pinnacle (WR Water) appears in 5 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2018-19 Q2.
Its cost is $2.1m at 2018-19 Q2, against $0.9m at its baseline: +126%.
Its planned finish is 27 Nov 2018, 2 months later than the 30 Sep 2018 first planned.
Its latest rating is Green (2018-19 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Project Pinnacle. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/wrwaterprojectpinnacle, as at 18 May 2026. Licence: CC BY 4.0.
How much does Project Pinnacle cost? Its cost is $2.1m at 2018-19 Q2, against $0.9m at its baseline: +126%.
Is Project Pinnacle late? Its planned finish is 27 Nov 2018, 2 months later than the 30 Sep 2018 first planned.
What is Project Pinnacle's latest rating? Its latest rating is Green (2018-19 Q2).