Business Transformation Project (WPR Water) appears in 17 snapshots of the Victorian IT dashboard, from 2017-18 Q3 to 2021-22 Q3.
Its cost is $3.8m at 2021-22 Q3, against $2.0m at its baseline: +97%.
Its planned finish is 22 Feb 2022, 20 months later than the 30 Jun 2020 first planned.
Its latest rating is Amber (2021-22 Q3).