Oracle Exadata Platform Refresh (WorkSafe) appears in 5 snapshots of the Victorian IT dashboard, from 2024-25 Q2 to 2025-26 Q2.
Its planned finish is 28 Nov 2025, 1 months later than the 27 Oct 2025 first planned.
Its latest rating is Green (2025-26 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Oracle Exadata Platform Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/worksafeoracleexadataplatformrefresh, as at 18 May 2026. Licence: CC BY 4.0.
Is Oracle Exadata Platform Refresh late? Its planned finish is 28 Nov 2025, 1 months later than the 27 Oct 2025 first planned.
What is Oracle Exadata Platform Refresh's latest rating? Its latest rating is Green (2025-26 Q2).