Medical Panels Capability Uplift (WorkSafe) appears in 7 snapshots of the Victorian IT dashboard, from 2023-24 Q4 to 2025-26 Q2.
Its cost is $4.9m at 2025-26 Q2, against $5.0m at its baseline: -2%.
Its planned finish is 30 Jun 2026, 8 months later than the 31 Oct 2025 first planned.
Its latest rating is Amber (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Medical Panels Capability Uplift. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/worksafemedicalpanelscapabilityuplift, as at 18 May 2026. Licence: CC BY 4.0.
How much does Medical Panels Capability Uplift cost? Its cost is $4.9m at 2025-26 Q2, against $5.0m at its baseline: -2%.
Is Medical Panels Capability Uplift late? Its planned finish is 30 Jun 2026, 8 months later than the 31 Oct 2025 first planned.
What is Medical Panels Capability Uplift's latest rating? Its latest rating is Amber (2025-26 Q2).