Inspectors Toolkit (WorkSafe) appears in 11 snapshots of the Victorian IT dashboard, from 2018-19 Q4 to 2021-22 Q2.
Its cost is $1.7m at 2021-22 Q2, against $1.5m at its baseline: +17%.
Its planned finish is 30 Nov 2021, 20 months later than the 7 Apr 2020 first planned.
Its latest rating is Green (2021-22 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Inspectors Toolkit. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/worksafeinspectorstoolkit, as at 18 May 2026. Licence: CC BY 4.0.
How much does Inspectors Toolkit cost? Its cost is $1.7m at 2021-22 Q2, against $1.5m at its baseline: +17%.
Is Inspectors Toolkit late? Its planned finish is 30 Nov 2021, 20 months later than the 7 Apr 2020 first planned.
What is Inspectors Toolkit's latest rating? Its latest rating is Green (2021-22 Q2).