IBM Transformation (WorkSafe) appears in 5 snapshots of the Victorian IT dashboard, from 2017-18 Q4 to 2018-19 Q4.
Its cost is $3.8m at 2018-19 Q4, against $2.4m at its baseline: +56%.
Its planned finish is 30 Jun 2019, 7 months later than the 10 Dec 2018 first planned.
Its latest rating is Green (2018-19 Q4), up from Amber at 2017-18 Q4.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: IBM Transformation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/worksafeibmtransformation, as at 18 May 2026. Licence: CC BY 4.0.
How much does IBM Transformation cost? Its cost is $3.8m at 2018-19 Q4, against $2.4m at its baseline: +56%.
Is IBM Transformation late? Its planned finish is 30 Jun 2019, 7 months later than the 10 Dec 2018 first planned.
What is IBM Transformation's latest rating? Its latest rating is Green (2018-19 Q4), up from Amber at 2017-18 Q4.