IAAS Transition (WorkSafe) appears in 6 snapshots of the Victorian IT dashboard, from 2017-18 Q4 to 2019-20 Q1.
Its cost is $1.1m at 2019-20 Q1, against $0.8m at its baseline: +29%.
Its planned finish is 30 Sep 2019, 15 months later than the 30 Jun 2018 first planned.
Its latest rating is Green (2019-20 Q1), up from Amber at 2017-18 Q4.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: IAAS Transition. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/worksafeiaastransition, as at 18 May 2026. Licence: CC BY 4.0.
How much does IAAS Transition cost? Its cost is $1.1m at 2019-20 Q1, against $0.8m at its baseline: +29%.
Is IAAS Transition late? Its planned finish is 30 Sep 2019, 15 months later than the 30 Jun 2018 first planned.
What is IAAS Transition's latest rating? Its latest rating is Green (2019-20 Q1), up from Amber at 2017-18 Q4.