Workforce management (V/Line) appears in 19 snapshots of the Victorian IT dashboard, from 2020-21 Q1 to 2025-26 Q2.
Its cost is $10.0m at 2025-26 Q2, against $9.7m at its baseline: +3%.
Its planned finish is 31 Dec 2026, 5 months later than the 31 Jul 2026 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Workforce management. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vlineworkforcemanagement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Workforce management cost? Its cost is $10.0m at 2025-26 Q2, against $9.7m at its baseline: +3%.
Is Workforce management late? Its planned finish is 31 Dec 2026, 5 months later than the 31 Jul 2026 first planned.
What is Workforce management's latest rating? Its latest rating is Green (2025-26 Q2).