TRACKR Development (V/Line) appears in 13 snapshots of the Victorian IT dashboard, from 2017-18 Q1 to 2020-21 Q2.
Its cost is $4.5m at 2020-21 Q2, against $1.4m at its baseline: +217%.
Its planned finish is 30 Oct 2020, 22 months later than the 31 Dec 2018 first planned.
Its latest rating is Green (2020-21 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: TRACKR Development. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vlinetrackrdevelopment, as at 18 May 2026. Licence: CC BY 4.0.
How much does TRACKR Development cost? Its cost is $4.5m at 2020-21 Q2, against $1.4m at its baseline: +217%.
Is TRACKR Development late? Its planned finish is 30 Oct 2020, 22 months later than the 31 Dec 2018 first planned.
What is TRACKR Development's latest rating? Its latest rating is Green (2020-21 Q2).