VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 (VicTrack) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $2.8m at 2017-18 Q2, against $1.4m at its baseline: +97%.
Its planned finish is 20 Dec 2017, 18 months later than the 29 Jun 2016 first planned.
Its latest rating is Red (2017-18 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/victrackvictracktelecommunicationsservicemanagementsystemtsmsimplementationphase1, as at 18 May 2026. Licence: CC BY 4.0.
How much does VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 cost? Its cost is $2.8m at 2017-18 Q2, against $1.4m at its baseline: +97%.
Is VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 late? Its planned finish is 20 Dec 2017, 18 months later than the 29 Jun 2016 first planned.
What is VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1's latest rating? Its latest rating is Red (2017-18 Q2).