PIPP Transformation (VicPol) appears in 2 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2017-18 Q3.
Its cost is $8.9m at 2017-18 Q3, against $11m at its baseline: -19%.
Its planned finish is 30 Nov 2017, 8 months later than the 30 Mar 2017 first planned.
Its latest rating is Green (2017-18 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: PIPP Transformation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vicpolpipptransformation, as at 18 May 2026. Licence: CC BY 4.0.
How much does PIPP Transformation cost? Its cost is $8.9m at 2017-18 Q3, against $11m at its baseline: -19%.
Is PIPP Transformation late? Its planned finish is 30 Nov 2017, 8 months later than the 30 Mar 2017 first planned.
What is PIPP Transformation's latest rating? Its latest rating is Green (2017-18 Q3).