Enterprise Rostering (VicPol) appears in 16 snapshots of the Victorian IT dashboard, from 2021-22 Q3 to 2025-26 Q2.
Its cost is $21m at 2025-26 Q2, against $21m at its baseline: no change.
Its planned finish is 30 Sep 2025, 9 months later than the 31 Dec 2024 first planned.
Its latest rating is Red (2025-26 Q2), down from Green at 2021-22 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Enterprise Rostering. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vicpolenterpriserostering, as at 18 May 2026. Licence: CC BY 4.0.
How much does Enterprise Rostering cost? Its cost is $21m at 2025-26 Q2, against $21m at its baseline: no change.
Is Enterprise Rostering late? Its planned finish is 30 Sep 2025, 9 months later than the 31 Dec 2024 first planned.
What is Enterprise Rostering's latest rating? Its latest rating is Red (2025-26 Q2), down from Green at 2021-22 Q3.