Data Centre Relocation (VicPol) appears in 6 snapshots of the Victorian IT dashboard, from 2018-19 Q2 to 2019-20 Q3.
Its cost is $16m at 2019-20 Q3, against $15m at its baseline: +7%.
Its planned finish is 12 Mar 2020, 2 months later than the 30 Dec 2019 first planned.
Its latest rating is Green (2019-20 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Data Centre Relocation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vicpoldatacentrerelocation, as at 18 May 2026. Licence: CC BY 4.0.
How much does Data Centre Relocation cost? Its cost is $16m at 2019-20 Q3, against $15m at its baseline: +7%.
Is Data Centre Relocation late? Its planned finish is 12 Mar 2020, 2 months later than the 30 Dec 2019 first planned.
What is Data Centre Relocation's latest rating? Its latest rating is Green (2019-20 Q3).