BlueConnect - Intelligence Management (VicPol) appears in 12 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2020-21 Q1.
Its cost is $106m at 2020-21 Q1, against $103m at its baseline: +3%.
Its planned finish is 30 Jun 2020, 12 months earlier than the 30 Jun 2021 first planned.
Its latest rating is Green (2020-21 Q1), up from Amber at 2017-18 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: BlueConnect - Intelligence Management. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vicpolblueconnectintelligencemanagement, as at 18 May 2026. Licence: CC BY 4.0.
How much does BlueConnect - Intelligence Management cost? Its cost is $106m at 2020-21 Q1, against $103m at its baseline: +3%.
Is BlueConnect - Intelligence Management late? Its planned finish is 30 Jun 2020, 12 months earlier than the 30 Jun 2021 first planned.
What is BlueConnect - Intelligence Management's latest rating? Its latest rating is Green (2020-21 Q1), up from Amber at 2017-18 Q2.