Roll Managment System (RMS) Technical Upgrade (VEC) appears in 8 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2025-26 Q1.
Its cost is $8.5m at 2025-26 Q1, against $7.8m at its baseline: +8%.
Its planned finish is 24 Oct 2025, 1 months later than the 30 Sep 2025 first planned.
Its latest rating is Green (2025-26 Q1), up from Amber at 2023-24 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Roll Managment System (RMS) Technical Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vecrollmanagmentsystemrmstechnicalupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does Roll Managment System (RMS) Technical Upgrade cost? Its cost is $8.5m at 2025-26 Q1, against $7.8m at its baseline: +8%.
Is Roll Managment System (RMS) Technical Upgrade late? Its planned finish is 24 Oct 2025, 1 months later than the 30 Sep 2025 first planned.
What is Roll Managment System (RMS) Technical Upgrade's latest rating? Its latest rating is Green (2025-26 Q1), up from Amber at 2023-24 Q2.