Building Practitioner System (VBA) appears in 6 snapshots of the Victorian IT dashboard, from 2022-23 Q1 to 2023-24 Q2.
Its cost is $4.6m at 2023-24 Q2, against $2.5m at its baseline: +85%.
Its planned finish is 31 Oct 2023, 5 months later than the 26 May 2023 first planned.
Its latest rating is Green (2023-24 Q2), up from Amber at 2022-23 Q1.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Building Practitioner System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vbabuildingpractitionersystem, as at 18 May 2026. Licence: CC BY 4.0.
How much does Building Practitioner System cost? Its cost is $4.6m at 2023-24 Q2, against $2.5m at its baseline: +85%.
Is Building Practitioner System late? Its planned finish is 31 Oct 2023, 5 months later than the 26 May 2023 first planned.
What is Building Practitioner System's latest rating? Its latest rating is Green (2023-24 Q2), up from Amber at 2022-23 Q1.