Building Activity Management System (BAMS) (VBA) appears in 4 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2018-19 Q4.
Its cost is $3.5m at 2018-19 Q4, against $2.0m at its baseline: +75%.
Its latest rating is Green (2018-19 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Building Activity Management System (BAMS). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/vbabuildingactivitymanagementsystembams, as at 18 May 2026. Licence: CC BY 4.0.
How much does Building Activity Management System (BAMS) cost? Its cost is $3.5m at 2018-19 Q4, against $2.0m at its baseline: +75%.
What is Building Activity Management System (BAMS)'s latest rating? Its latest rating is Green (2018-19 Q4).