Emergency Sector Integration Platform (TZV) appears in 8 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2025-26 Q1.
Its cost is $9.0m at 2025-26 Q1, against $5.1m at its baseline: +78%.
Its planned finish is 14 Jul 2025, 6 months later than the 31 Dec 2024 first planned.
Its latest rating is Green (2025-26 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Emergency Sector Integration Platform. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/tzvemergencysectorintegrationplatform, as at 18 May 2026. Licence: CC BY 4.0.
How much does Emergency Sector Integration Platform cost? Its cost is $9.0m at 2025-26 Q1, against $5.1m at its baseline: +78%.
Is Emergency Sector Integration Platform late? Its planned finish is 14 Jul 2025, 6 months later than the 31 Dec 2024 first planned.
What is Emergency Sector Integration Platform's latest rating? Its latest rating is Green (2025-26 Q1).