Alternate CAD (TZV) appears in 5 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2024-25 Q2.
Its cost is $4.3m at 2024-25 Q2, against $5.4m at its baseline: -21%.
Its planned finish is 19 Dec 2024, 10 months later than the 29 Feb 2024 first planned.
Its latest rating is Red (2024-25 Q2), down from Green at 2023-24 Q2.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Alternate CAD. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/tzvalternatecad, as at 18 May 2026. Licence: CC BY 4.0.
How much does Alternate CAD cost? Its cost is $4.3m at 2024-25 Q2, against $5.4m at its baseline: -21%.
Is Alternate CAD late? Its planned finish is 19 Dec 2024, 10 months later than the 29 Feb 2024 first planned.
What is Alternate CAD's latest rating? Its latest rating is Red (2024-25 Q2), down from Green at 2023-24 Q2.