Treasury System Review (TCV) appears in 2 snapshots of the Victorian IT dashboard, from 2017-18 Q3 to 2017-18 Q4.
Its cost is $1.9m at 2017-18 Q4, against $2.4m at its baseline: -19%.
Its planned finish is 31 May 2018, 5 months later than the 31 Dec 2017 first planned.
Its latest rating is Green (2017-18 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Treasury System Review. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/tcvtreasurysystemreview, as at 18 May 2026. Licence: CC BY 4.0.
How much does Treasury System Review cost? Its cost is $1.9m at 2017-18 Q4, against $2.4m at its baseline: -19%.
Is Treasury System Review late? Its planned finish is 31 May 2018, 5 months later than the 31 Dec 2017 first planned.
What is Treasury System Review's latest rating? Its latest rating is Green (2017-18 Q4).