Intelligent Information Management (TAC) appears in 5 snapshots of the Victorian IT dashboard, from 2023-24 Q2 to 2024-25 Q2.
Its cost is $1.5m at 2024-25 Q2, against $1.2m at its baseline: +27%.
Its planned finish is 20 Dec 2024, 6 months later than the 30 Jun 2024 first planned.
Its latest rating is Green (2024-25 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Intelligent Information Management. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/tacintelligentinformationmanagement, as at 18 May 2026. Licence: CC BY 4.0.
How much does Intelligent Information Management cost? Its cost is $1.5m at 2024-25 Q2, against $1.2m at its baseline: +27%.
Is Intelligent Information Management late? Its planned finish is 20 Dec 2024, 6 months later than the 30 Jun 2024 first planned.
What is Intelligent Information Management's latest rating? Its latest rating is Green (2024-25 Q2).