IAAS Transition (TAC) (TAC) appears in 3 snapshots of the Victorian IT dashboard, from 2018-19 Q2 to 2018-19 Q4.
Its cost is $1.4m at 2018-19 Q4, against $1.3m at its baseline: +2%.
Its planned finish is 30 Jun 2019, 12 months later than the 30 Jun 2018 first planned.
Its latest rating is Green (2018-19 Q4), up from Amber at 2018-19 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: IAAS Transition (TAC). Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/taciaastransitiontac, as at 18 May 2026. Licence: CC BY 4.0.
How much does IAAS Transition (TAC) cost? Its cost is $1.4m at 2018-19 Q4, against $1.3m at its baseline: +2%.
Is IAAS Transition (TAC) late? Its planned finish is 30 Jun 2019, 12 months later than the 30 Jun 2018 first planned.
What is IAAS Transition (TAC)'s latest rating? Its latest rating is Green (2018-19 Q4), up from Amber at 2018-19 Q2.