Continuous Delivery 2022 (TAC) appears in 4 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2021-22 Q4.
Its cost is $3.8m at 2021-22 Q4, against $3.3m at its baseline: +16%.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Continuous Delivery 2022. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/taccontinuousdelivery2022, as at 18 May 2026. Licence: CC BY 4.0.
How much does Continuous Delivery 2022 cost? Its cost is $3.8m at 2021-22 Q4, against $3.3m at its baseline: +16%.
What is Continuous Delivery 2022's latest rating? Its latest rating is Green (2021-22 Q4).