AV Uplift TAC (TAC) appears in 14 snapshots of the Victorian IT dashboard, from 2019-20 Q4 to 2023-24 Q1.
Its cost is $3.4m at 2023-24 Q1, against $1.6m at its baseline: +112%.
Its planned finish is 30 Sep 2023, 33 months later than the 31 Dec 2020 first planned.
Its latest rating is Green (2023-24 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: AV Uplift TAC. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/tacavuplifttac, as at 18 May 2026. Licence: CC BY 4.0.
How much does AV Uplift TAC cost? Its cost is $3.4m at 2023-24 Q1, against $1.6m at its baseline: +112%.
Is AV Uplift TAC late? Its planned finish is 30 Sep 2023, 33 months later than the 31 Dec 2020 first planned.
What is AV Uplift TAC's latest rating? Its latest rating is Green (2023-24 Q1).