PACS Replacement (SWARH) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q3 to 2025-26 Q2.
Its planned finish is 27 Feb 2026, 4 months later than the 30 Oct 2025 first planned.
Its latest rating is Red (2025-26 Q2), down from Green at 2024-25 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: PACS Replacement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/swarhpacsreplacement, as at 18 May 2026. Licence: CC BY 4.0.
Is PACS Replacement late? Its planned finish is 27 Feb 2026, 4 months later than the 30 Oct 2025 first planned.
What is PACS Replacement's latest rating? Its latest rating is Red (2025-26 Q2), down from Green at 2024-25 Q3.