Barwon Health Rebuild of PROMPT Document Management System (SWARH) appears in 6 snapshots of the Victorian IT dashboard, from 2018-19 Q2 to 2019-20 Q3.
Its planned finish is 25 Feb 2020, 8 months later than the 30 Jun 2019 first planned.
Its latest rating is Green (2019-20 Q3), up from Amber at 2018-19 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Barwon Health Rebuild of PROMPT Document Management System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/swarhbarwonhealthrebuildofpromptdocumentmanagementsystem, as at 18 May 2026. Licence: CC BY 4.0.
Is Barwon Health Rebuild of PROMPT Document Management System late? Its planned finish is 25 Feb 2020, 8 months later than the 30 Jun 2019 first planned.
What is Barwon Health Rebuild of PROMPT Document Management System's latest rating? Its latest rating is Green (2019-20 Q3), up from Amber at 2018-19 Q2.