Barwon Health Optima Rostering Project (SWARH) appears in 10 snapshots of the Victorian IT dashboard, from 2020-21 Q2 to 2022-23 Q3.
Its cost is $7.3m at 2022-23 Q3, against $3.4m at its baseline: +113%.
Its planned finish is 31 Oct 2024, 58 months later than the 31 Dec 2019 first planned.
Its latest rating is Green (2022-23 Q3), up from Red at 2020-21 Q2.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Barwon Health Optima Rostering Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/swarhbarwonhealthoptimarosteringproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does Barwon Health Optima Rostering Project cost? Its cost is $7.3m at 2022-23 Q3, against $3.4m at its baseline: +113%.
Is Barwon Health Optima Rostering Project late? Its planned finish is 31 Oct 2024, 58 months later than the 31 Dec 2019 first planned.
What is Barwon Health Optima Rostering Project's latest rating? Its latest rating is Green (2022-23 Q3), up from Red at 2020-21 Q2.