Barwon Health North - ICT Infrastructure (SWARH) appears in 5 snapshots of the Victorian IT dashboard, from 2019-20 Q4 to 2020-21 Q4.
Its cost is $1.2m at 2020-21 Q4, against $1.2m at its baseline: +8%.
Its planned finish is 29 Feb 2020, 6 months later than the 30 Aug 2019 first planned.
Its latest rating is Green (2020-21 Q4), up from Amber at 2019-20 Q4.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Barwon Health North - ICT Infrastructure. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/swarhbarwonhealthnorthictinfrastructure, as at 18 May 2026. Licence: CC BY 4.0.
How much does Barwon Health North - ICT Infrastructure cost? Its cost is $1.2m at 2020-21 Q4, against $1.2m at its baseline: +8%.
Is Barwon Health North - ICT Infrastructure late? Its planned finish is 29 Feb 2020, 6 months later than the 30 Aug 2019 first planned.
What is Barwon Health North - ICT Infrastructure's latest rating? Its latest rating is Green (2020-21 Q4), up from Amber at 2019-20 Q4.