Short Stay Levy (SRO) appears in 5 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q1.
Its cost is $3.1m at 2025-26 Q1, against $3.1m at its baseline: +1%.
Its planned finish is 30 Aug 2025, 2 months later than the 30 Jun 2025 first planned.
Its latest rating is Green (2025-26 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Short Stay Levy. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sroshortstaylevy, as at 18 May 2026. Licence: CC BY 4.0.
How much does Short Stay Levy cost? Its cost is $3.1m at 2025-26 Q1, against $3.1m at its baseline: +1%.
Is Short Stay Levy late? Its planned finish is 30 Aug 2025, 2 months later than the 30 Jun 2025 first planned.
What is Short Stay Levy's latest rating? Its latest rating is Green (2025-26 Q1).