LPR #2&3 - Land Ownership, NOAs and Land Usage Vicroads. (SRO) appears in 10 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2019-20 Q3.
Its cost is $4.2m at 2019-20 Q3, against $3.9m at its baseline: +7%.
Its planned finish is 26 Mar 2020, 23 months later than the 13 Apr 2018 first planned.
Its latest rating is Green (2019-20 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: LPR #2&3 - Land Ownership, NOAs and Land Usage Vicroads.. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/srolpr23landownershipnoasandlandusagevicroads, as at 18 May 2026. Licence: CC BY 4.0.
How much does LPR #2&3 - Land Ownership, NOAs and Land Usage Vicroads. cost? Its cost is $4.2m at 2019-20 Q3, against $3.9m at its baseline: +7%.
Is LPR #2&3 - Land Ownership, NOAs and Land Usage Vicroads. late? Its planned finish is 26 Mar 2020, 23 months later than the 13 Apr 2018 first planned.
What is LPR #2&3 - Land Ownership, NOAs and Land Usage Vicroads.'s latest rating? Its latest rating is Green (2019-20 Q3).