Digital Duties Program (SRO) appears in 12 snapshots of the Victorian IT dashboard, from 2018-19 Q1 to 2020-21 Q4.
Its cost is $2.9m at 2020-21 Q4, against $1.4m at its baseline: +110%.
Its planned finish is 30 Jun 2021, 17 months later than the 17 Jan 2020 first planned.
Its latest rating is Green (2020-21 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Digital Duties Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/srodigitaldutiesprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Digital Duties Program cost? Its cost is $2.9m at 2020-21 Q4, against $1.4m at its baseline: +110%.
Is Digital Duties Program late? Its planned finish is 30 Jun 2021, 17 months later than the 17 Jan 2020 first planned.
What is Digital Duties Program's latest rating? Its latest rating is Green (2020-21 Q4).