Data Centre Relocation and Uplift (SRO) appears in 8 snapshots of the Victorian IT dashboard, from 2020-21 Q1 to 2021-22 Q4.
Its cost is $3.0m at 2021-22 Q4, against $1.7m at its baseline: +80%.
Its planned finish is 31 May 2022, 11 months later than the 30 Jun 2021 first planned.
Its latest rating is Green (2021-22 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Data Centre Relocation and Uplift. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/srodatacentrerelocationanduplift, as at 18 May 2026. Licence: CC BY 4.0.
How much does Data Centre Relocation and Uplift cost? Its cost is $3.0m at 2021-22 Q4, against $1.7m at its baseline: +80%.
Is Data Centre Relocation and Uplift late? Its planned finish is 31 May 2022, 11 months later than the 30 Jun 2021 first planned.
What is Data Centre Relocation and Uplift's latest rating? Its latest rating is Green (2021-22 Q4).