Next Gen Business System Program (SMCT) appears in 15 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2024-25 Q3.
Its planned finish is 31 Jan 2025, 14 months later than the 24 Nov 2023 first planned.
Its latest rating is Green (2024-25 Q3).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Next Gen Business System Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/smctnextgenbusinesssystemprogram, as at 18 May 2026. Licence: CC BY 4.0.
Is Next Gen Business System Program late? Its planned finish is 31 Jan 2025, 14 months later than the 24 Nov 2023 first planned.
What is Next Gen Business System Program's latest rating? Its latest rating is Green (2024-25 Q3).