PULSE CX Optimisation Phase 1 (SE Water) appears in one Victorian IT dashboard snapshot, 2024-25 Q1.
Its cost is $1.9m at 2024-25 Q1, against $1.8m at its baseline: +2%.
Its latest rating is Green (2024-25 Q1).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: PULSE CX Optimisation Phase 1. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sewaterpulsecxoptimisationphase1, as at 18 May 2026. Licence: CC BY 4.0.
How much does PULSE CX Optimisation Phase 1 cost? Its cost is $1.9m at 2024-25 Q1, against $1.8m at its baseline: +2%.
What is PULSE CX Optimisation Phase 1's latest rating? Its latest rating is Green (2024-25 Q1).