Meeting Room Technology Upgrade (SE Water) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2024-25 Q4.
Its cost is $1.0m at 2024-25 Q4, against $1.0m at its baseline: +1%.
Its planned finish is 30 Apr 2025, 4 months later than the 31 Dec 2024 first planned.
Its latest rating is Green (2024-25 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Meeting Room Technology Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sewatermeetingroomtechnologyupgrade, as at 18 May 2026. Licence: CC BY 4.0.
How much does Meeting Room Technology Upgrade cost? Its cost is $1.0m at 2024-25 Q4, against $1.0m at its baseline: +1%.
Is Meeting Room Technology Upgrade late? Its planned finish is 30 Apr 2025, 4 months later than the 31 Dec 2024 first planned.
What is Meeting Room Technology Upgrade's latest rating? Its latest rating is Green (2024-25 Q4).