CRUX - Stabilisation (SE Water) appears in 4 snapshots of the Victorian IT dashboard, from 2024-25 Q3 to 2025-26 Q2.
Its cost is $4.0m at 2025-26 Q2, against $3.5m at its baseline: +14%.
Its planned finish is 30 Apr 2026, 3 months later than the 30 Jan 2026 first planned.
Its latest rating is Amber (2025-26 Q2), down from Green at 2024-25 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: CRUX - Stabilisation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sewatercruxstabilisation, as at 18 May 2026. Licence: CC BY 4.0.
How much does CRUX - Stabilisation cost? Its cost is $4.0m at 2025-26 Q2, against $3.5m at its baseline: +14%.
Is CRUX - Stabilisation late? Its planned finish is 30 Apr 2026, 3 months later than the 30 Jan 2026 first planned.
What is CRUX - Stabilisation's latest rating? Its latest rating is Amber (2025-26 Q2), down from Green at 2024-25 Q3.