CRUX (SE Water) appears in 7 snapshots of the Victorian IT dashboard, from 2021-22 Q4 to 2023-24 Q2.
Its cost is $12m at 2023-24 Q2, against $6.5m at its baseline: +86%.
Its planned finish is 30 Nov 2023, 4 months later than the 4 Aug 2023 first planned.
Its latest rating is Green (2023-24 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: CRUX. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sewatercrux, as at 18 May 2026. Licence: CC BY 4.0.
How much does CRUX cost? Its cost is $12m at 2023-24 Q2, against $6.5m at its baseline: +86%.
Is CRUX late? Its planned finish is 30 Nov 2023, 4 months later than the 4 Aug 2023 first planned.
What is CRUX's latest rating? Its latest rating is Green (2023-24 Q2).