Acumen Phase 2 (SE Water) appears in 6 snapshots of the Victorian IT dashboard, from 2024-25 Q1 to 2025-26 Q2.
Its cost is $6.6m at 2025-26 Q2, against $3.6m at its baseline: +83%.
Its planned finish is 28 Feb 2026, 10 months later than the 30 Apr 2025 first planned.
Its latest rating is Green (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Acumen Phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/sewateracumenphase2, as at 18 May 2026. Licence: CC BY 4.0.
How much does Acumen Phase 2 cost? Its cost is $6.6m at 2025-26 Q2, against $3.6m at its baseline: +83%.
Is Acumen Phase 2 late? Its planned finish is 28 Feb 2026, 10 months later than the 30 Apr 2025 first planned.
What is Acumen Phase 2's latest rating? Its latest rating is Green (2025-26 Q2).