Digital Train Radio System (DTRS) Obsolescence Upgrades Program (PTV) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its cost is $16m at 2017-18 Q2, against $16m at its baseline: -2%.
Its planned finish is 30 Nov 2018, 1 months later than the 10 Nov 2018 first planned.
Its latest rating is Green (2017-18 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Digital Train Radio System (DTRS) Obsolescence Upgrades Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/ptvdigitaltrainradiosystemdtrsobsolescenceupgradesprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Digital Train Radio System (DTRS) Obsolescence Upgrades Program cost? Its cost is $16m at 2017-18 Q2, against $16m at its baseline: -2%.
Is Digital Train Radio System (DTRS) Obsolescence Upgrades Program late? Its planned finish is 30 Nov 2018, 1 months later than the 10 Nov 2018 first planned.
What is Digital Train Radio System (DTRS) Obsolescence Upgrades Program's latest rating? Its latest rating is Green (2017-18 Q2).