Bus Passenger Information Displays (PIDs) Implementation Program (PTV) appears in 9 snapshots of the Victorian IT dashboard, from 2016-17 Q4 to 2018-19 Q4.
Its cost is $1.2m at 2018-19 Q4, against $1.1m at its baseline: +9%.
Its planned finish is 31 Jul 2019, 16 months later than the 5 Apr 2018 first planned.
Its latest rating is Green (2018-19 Q4).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Bus Passenger Information Displays (PIDs) Implementation Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/ptvbuspassengerinformationdisplayspidsimplementationprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Bus Passenger Information Displays (PIDs) Implementation Program cost? Its cost is $1.2m at 2018-19 Q4, against $1.1m at its baseline: +9%.
Is Bus Passenger Information Displays (PIDs) Implementation Program late? Its planned finish is 31 Jul 2019, 16 months later than the 5 Apr 2018 first planned.
What is Bus Passenger Information Displays (PIDs) Implementation Program's latest rating? Its latest rating is Green (2018-19 Q4).