Bus Information Improvement Project (PTV) appears in one Victorian IT dashboard snapshot, 2017-18 Q2.
Its planned finish is 16 Oct 2017, 15 months later than the 29 Jul 2016 first planned.
Its latest rating is Green (2017-18 Q2).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Bus Information Improvement Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/ptvbusinformationimprovementproject, as at 18 May 2026. Licence: CC BY 4.0.
Is Bus Information Improvement Project late? Its planned finish is 16 Oct 2017, 15 months later than the 29 Jul 2016 first planned.
What is Bus Information Improvement Project's latest rating? Its latest rating is Green (2017-18 Q2).