Digital Archive Program (PROV) appears in 22 snapshots of the Victorian IT dashboard, from 2017-18 Q2 to 2022-23 Q3.
Its cost is $5.6m at 2022-23 Q3, against $4.1m at its baseline: +38%.
Its planned finish is 31 Mar 2023, 57 months later than the 30 Jun 2018 first planned.
Its latest rating is Green (2022-23 Q3), up from Amber at 2017-18 Q2.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Digital Archive Program. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/provdigitalarchiveprogram, as at 18 May 2026. Licence: CC BY 4.0.
How much does Digital Archive Program cost? Its cost is $5.6m at 2022-23 Q3, against $4.1m at its baseline: +38%.
Is Digital Archive Program late? Its planned finish is 31 Mar 2023, 57 months later than the 30 Jun 2018 first planned.
What is Digital Archive Program's latest rating? Its latest rating is Green (2022-23 Q3), up from Amber at 2017-18 Q2.