People and Payroll Transformation Program - Rostering Project (Peter MAC) appears in 18 snapshots of the Victorian IT dashboard, from 2021-22 Q1 to 2025-26 Q2.
Its cost is $12m at 2025-26 Q2, against $6.4m at its baseline: +84%.
Its planned finish is 30 Jun 2026, 12 months later than the 30 Jun 2025 first planned.
Its latest rating is Red (2025-26 Q2).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: People and Payroll Transformation Program - Rostering Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/petermacpeopleandpayrolltransformationprogramrosteringproject, as at 18 May 2026. Licence: CC BY 4.0.
How much does People and Payroll Transformation Program - Rostering Project cost? Its cost is $12m at 2025-26 Q2, against $6.4m at its baseline: +84%.
Is People and Payroll Transformation Program - Rostering Project late? Its planned finish is 30 Jun 2026, 12 months later than the 30 Jun 2025 first planned.
What is People and Payroll Transformation Program - Rostering Project's latest rating? Its latest rating is Red (2025-26 Q2).